ExamGecko
Home / PMI / PMP / Practice Test 6
Ask Question

PMI PMP Practice Test 6

Add to Whishlist
00:00:00
Show Answer
Report Issue   Restart test

Question 1 / 40

A project manager is working on a multinational project that has more than 100 stakeholders. The project manager is concerned about the appropriate stakeholder participation and involvement level required for successful project delivery.

What should the project manager do?

Communicate with the stakeholders to find a solution.
Communicate with the stakeholders to find a solution.
Review the issue log with the project stakeholders.
Review the issue log with the project stakeholders.
Evaluate the stakeholder engagement assessment matrix.
Evaluate the stakeholder engagement assessment matrix.
Perform a stakeholder assumption and constraint analysis.
Perform a stakeholder assumption and constraint analysis.
Comment (0)
Suggested answer: C
asked 23/09/2024
Pablo Magallanes
44 questions