Scrum PSM I Practice Test - Questions Answers, Page 7

Question list
Search
Search

Related questions











The Product Owner is not collaborating with the Development Team during the Sprint. What are two valuable actions for a Scrum Master to take? (Choose two.)

A.
Inform the Product Owner's functional manager.
A.
Inform the Product Owner's functional manager.
Answers
B.
Stop the Sprint, send the Product Owner to a course and restart.
B.
Stop the Sprint, send the Product Owner to a course and restart.
Answers
C.
Bring up the problem in the Sprint Retrospective.
C.
Bring up the problem in the Sprint Retrospective.
Answers
D.
Coach the Product Owner in the values of Scrum and incremental delivery.
D.
Coach the Product Owner in the values of Scrum and incremental delivery.
Answers
E.
Nominate a proxy Product Owner.
E.
Nominate a proxy Product Owner.
Answers
Suggested answer: C, D

Multiple Scrum Teams working on the same product or system all select work from the same Product Backlog.

A.
True
A.
True
Answers
B.
False
B.
False
Answers
Suggested answer: A

For the purpose of transparency, when does Scrum say a valuable and useful increment must be available?

A.
After the acceptance testing phase.
A.
After the acceptance testing phase.
Answers
B.
Before the release Sprint.
B.
Before the release Sprint.
Answers
C.
Every 3 Sprints.
C.
Every 3 Sprints.
Answers
D.
At the end of every Sprint.
D.
At the end of every Sprint.
Answers
E.
When the Product Owner asks to create one.
E.
When the Product Owner asks to create one.
Answers
Suggested answer: D

Multiple Scrum Teams working on the same project must have the same Sprint start date.

A.
True
A.
True
Answers
B.
False
B.
False
Answers
Suggested answer: B

What is a Development Team responsible for? (Choose two.)

A.
Resolving internal team conflicts.
A.
Resolving internal team conflicts.
Answers
B.
Reporting productivity.
B.
Reporting productivity.
Answers
C.
Selecting the Product Owner.
C.
Selecting the Product Owner.
Answers
D.
Organizing the work required to meet the Sprint Goal.
D.
Organizing the work required to meet the Sprint Goal.
Answers
Suggested answer: A, D

Which two ways of creating Development Teams are consistent with Scrum's values? (Choose two.)

A.
Existing teams propose how they would like to go about organizing into the new structure.
A.
Existing teams propose how they would like to go about organizing into the new structure.
Answers
B.
Managers personally re-assign current subordinates to new teams.
B.
Managers personally re-assign current subordinates to new teams.
Answers
C.
Managers collaborate to assign individuals to specific teams.
C.
Managers collaborate to assign individuals to specific teams.
Answers
D.
Bring all the developers together and let them self-organize into Development Teams.
D.
Bring all the developers together and let them self-organize into Development Teams.
Answers
E.
The Chief Product Owner determines the new team structures and assignments.
E.
The Chief Product Owner determines the new team structures and assignments.
Answers
Suggested answer: A, D

A Scrum Master is essentially the same thing as a traditional PM (Project Manager).

A.
True
A.
True
Answers
B.
False
B.
False
Answers
Suggested answer: B

A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give?

A.
Product Backlog items must be estimated in story points.
A.
Product Backlog items must be estimated in story points.
Answers
B.
Estimates are made by the Development Team.
B.
Estimates are made by the Development Team.
Answers
C.
Estimates must be in relative units.
C.
Estimates must be in relative units.
Answers
D.
Scrum forbids estimating.
D.
Scrum forbids estimating.
Answers
E.
Estimates are made by the Product Owner, but are best checked with the Development Team.
E.
Estimates are made by the Product Owner, but are best checked with the Development Team.
Answers
Suggested answer: B

What is the time-box for the Sprint Planning meeting?

A.
4 Hours for a monthly Sprint.
A.
4 Hours for a monthly Sprint.
Answers
B.
8 Hours for a monthly Sprint.
B.
8 Hours for a monthly Sprint.
Answers
C.
Monthly.
C.
Monthly.
Answers
D.
Whenever it is done.
D.
Whenever it is done.
Answers
Suggested answer: B

Which Scrum Value is affected by a lack of trust in the Scrum Team?

A.
Focus
A.
Focus
Answers
B.
Respect
B.
Respect
Answers
C.
Openness
C.
Openness
Answers
D.
Courage
D.
Courage
Answers
E.
Commitment.
E.
Commitment.
Answers
F.
All of the above.
F.
All of the above.
Answers
Suggested answer: F