Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?

A.

Rollback plan

Answers
A.

Rollback plan

B.

Downtime stage

Answers
B.

Downtime stage

C.

Maintenance window

Answers
C.

Maintenance window

D.

Validation checks

Answers
D.

Validation checks

Suggested answer: A

Explanation:

A rollback plan is used when an issue is identified during testing or implementation. It allows the team to revert to the previous state, removing the new package. This aligns with CompTIA Project+ guidance on implementing fallback strategies for risk management.