Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?

A.

Sprint retrospective

Answers
A.

Sprint retrospective

B.

Sprint review

Answers
B.

Sprint review

C.

Sprint planning

Answers
C.

Sprint planning

D.

Daily Scrum

Answers
D.

Daily Scrum

Suggested answer: B

Explanation:

A Sprint Review involves reviewing the completed backlog items and presenting the work to stakeholders. This aligns with CompTIA Project+ agile practices, where a Sprint Review focuses on completed tasks and feedback.