A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?

A.

Quote

A.

Quote

Answers
B.

Information

B.

Information

Answers
C.

Proposal

C.

Proposal

Answers
D.

Bid

D.

Bid

Answers
Suggested answer: C

Explanation:

A proposal is a detailed document submitted by vendors outlining how they will meet project requirements. It helps in assessing vendor solutions and suitability, consistent with CompTIA Project+ procurement and vendor management practices.

Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?

A.

Sprint retrospective

A.

Sprint retrospective

Answers
B.

Sprint review

B.

Sprint review

Answers
C.

Sprint planning

C.

Sprint planning

Answers
D.

Daily Scrum

D.

Daily Scrum

Answers
Suggested answer: B

Explanation:

A Sprint Review involves reviewing the completed backlog items and presenting the work to stakeholders. This aligns with CompTIA Project+ agile practices, where a Sprint Review focuses on completed tasks and feedback.



Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?

A.

Rollback plan

A.

Rollback plan

Answers
B.

Downtime stage

B.

Downtime stage

Answers
C.

Maintenance window

C.

Maintenance window

Answers
D.

Validation checks

D.

Validation checks

Answers
Suggested answer: A

Explanation:

A rollback plan is used when an issue is identified during testing or implementation. It allows the team to revert to the previous state, removing the new package. This aligns with CompTIA Project+ guidance on implementing fallback strategies for risk management.

When assigning access, classifying information based on sensitivity is referred to as:

A.

Digital security

A.

Digital security

Answers
B.

Physical security

B.

Physical security

Answers
C.

Data security

C.

Data security

Answers
D.

Operational security

D.

Operational security

Answers
Suggested answer: C

Explanation:

Data security involves classifying information based on sensitivity and ensuring that it is protected accordingly. This approach is key in project management to protect sensitive data, as emphasized by CompTIA Project+.

A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?

A.

Reassigning resources

A.

Reassigning resources

Answers
B.

Removing access

B.

Removing access

Answers
C.

Closing contracts

C.

Closing contracts

Answers
D.

Evaluating the project

D.

Evaluating the project

Answers
Suggested answer: C

Explanation:

Closing contracts involves finalizing any remaining contractual obligations and formally closing out the relationship with the vendor. CompTIA Project+ emphasizes this as part of the project closure phase to ensure all legal and financial aspects are complete.

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?

A.

Hold the project until the devices are delivered.

A.

Hold the project until the devices are delivered.

Answers
B.

Evaluate the impact to baselines.

B.

Evaluate the impact to baselines.

Answers
C.

Request another supplier to ship devices.

C.

Request another supplier to ship devices.

Answers
D.

Update the project timeline with a new project end date.

D.

Update the project timeline with a new project end date.

Answers
Suggested answer: B

Explanation:

Evaluating the impact to baselines (such as schedule and budget) helps determine the delay's effect on the project. This aligns with CompTIA Project+ guidance on project control, which emphasizes analyzing impacts before taking corrective actions.

During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?

A.

Waterfall method

A.

Waterfall method

Answers
B.

Simulation method

B.

Simulation method

Answers
C.

Precedence diagramming method

C.

Precedence diagramming method

Answers
D.

Cost ratio analysis

D.

Cost ratio analysis

Answers
Suggested answer: C

Explanation:

The Precedence Diagramming Method (PDM) is used to visually represent tasks, dependencies, and sequencing in a project schedule. This technique is consistent with CompTIA Project+ guidelines for planning and managing project timelines.

A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?

A.

Discovery

A.

Discovery

Answers
B.

Execution

B.

Execution

Answers
C.

Initiating

C.

Initiating

Answers
D.

Planning

D.

Planning

Answers
Suggested answer: D

Explanation:

Defining communication channels and access requirements typically occurs in the planning phase, where detailed plans for project management are established. This aligns with CompTIA Project+ standards for comprehensive project planning.

A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?

A.

Assign a scribe to take notes.

A.

Assign a scribe to take notes.

Answers
B.

Record the meeting and transcribe the notes later.

B.

Record the meeting and transcribe the notes later.

Answers
C.

Instruct each team member to take notes.

C.

Instruct each team member to take notes.

Answers
D.

Get a facilitator for the meetings.

D.

Get a facilitator for the meetings.

Answers
Suggested answer: A

Explanation:

Assigning a scribe allows the project manager to focus on hosting and facilitating the meeting effectively without being distracted by note-taking. This approach is consistent with best practices in meeting management and aligns with CompTIA Project+ guidelines, which emphasize the importance of efficient meeting roles and responsibilities.

A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase. Which of the following types of testing should be done?

A.

Performance

A.

Performance

Answers
B.

Smoke

B.

Smoke

Answers
C.

Regression

C.

Regression

Answers
D.

Unit

D.

Unit

Answers
Suggested answer: B

Explanation:

Smoke testing is a preliminary test to check whether the most essential functions of the software work correctly. It is often the first step in the testing phase and helps confirm that the build is stable enough for further testing. This aligns with CompTIA Project+ practices for software testing phases.