A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?
A.
Hold the project until the devices are delivered.
B.
Evaluate the impact to baselines.
C.
Request another supplier to ship devices.
D.
Update the project timeline with a new project end date.