During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?

A.

Waterfall method

Answers
A.

Waterfall method

B.

Simulation method

Answers
B.

Simulation method

C.

Precedence diagramming method

Answers
C.

Precedence diagramming method

D.

Cost ratio analysis

Answers
D.

Cost ratio analysis

Suggested answer: C

Explanation:

The Precedence Diagramming Method (PDM) is used to visually represent tasks, dependencies, and sequencing in a project schedule. This technique is consistent with CompTIA Project+ guidelines for planning and managing project timelines.