A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?

A.

Discovery

Answers
A.

Discovery

B.

Execution

Answers
B.

Execution

C.

Initiating

Answers
C.

Initiating

D.

Planning

Answers
D.

Planning

Suggested answer: D

Explanation:

Defining communication channels and access requirements typically occurs in the planning phase, where detailed plans for project management are established. This aligns with CompTIA Project+ standards for comprehensive project planning.