ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 254 - PK0-005 discussion

Report
Export

During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?

A.

Hold a new backlog prioritization meeting.

Answers
A.

Hold a new backlog prioritization meeting.

B.

Add milestones to check the project's progress.

Answers
B.

Add milestones to check the project's progress.

C.

Adjust the task relationship to complete coding in advance.

Answers
C.

Adjust the task relationship to complete coding in advance.

D.

Apply contingency buffers to the critical path.

Answers
D.

Apply contingency buffers to the critical path.

Suggested answer: D

Explanation:

Adding contingency buffers to the critical path is a method to account for potential delays, increasing project certainty. This technique is part of risk management and schedule management, as recommended by CompTIA Project+.

asked 16/10/2024
Duane Joyce
33 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first