During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?
A.
Statement of work
B.
Business case
C.
Requirements document
D.
Work breakdown structure