Question 257 - PK0-005 discussion
A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?
A.
Key stakeholder identification
B.
Preliminary procurement
C.
Solution design determination
D.
Critical factor enlistment
Your answer: