Question 258 - PK0-005 discussion
A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?
A.
Update the WBS.
B.
Escalate to the CCB.
C.
Accept the change.
D.
Implement the change.