A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?

A.

Update the WBS.

Answers
A.

Update the WBS.

B.

Escalate to the CCB.

Answers
B.

Escalate to the CCB.

C.

Accept the change.

Answers
C.

Accept the change.

D.

Implement the change.

Answers
D.

Implement the change.

Suggested answer: B

Explanation:

Escalating to the Change Control Board (CCB) is necessary when a change request impacts the project's timeline or budget. The CCB reviews and approves changes, ensuring that they align with project objectives. CompTIA Project+ highlights the role of the CCB in change management processes.