Question 259 - PK0-005 discussion
During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?
A.
Some work packages are missing from the WBS.
B.
Information is missing from the RACI matrix.
C.
New knowledge bases were introduced.
D.
Team touch points are missing.
Your answer: