During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?

A.

Some work packages are missing from the WBS.

Answers
A.

Some work packages are missing from the WBS.

B.

Information is missing from the RACI matrix.

Answers
B.

Information is missing from the RACI matrix.

C.

New knowledge bases were introduced.

Answers
C.

New knowledge bases were introduced.

D.

Team touch points are missing.

Answers
D.

Team touch points are missing.

Suggested answer: B

Explanation:

A RACI matrix clarifies roles and responsibilities for tasks, reducing confusion and disagreements among team members. Missing or incomplete information in the RACI matrix could lead to disputes, as it is a key tool for accountability in project management per CompTIA Project+.