A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?
A.
Task log
B.
Cadence
C.
Milestones
D.
Work breakdown structure
Your answer: