A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?

A.

Identify project risks and plans to address them.

Answers
A.

Identify project risks and plans to address them.

B.

Identify business needs and product descriptions.

Answers
B.

Identify business needs and product descriptions.

C.

Create a work breakdown structure for the project.

Answers
C.

Create a work breakdown structure for the project.

D.

Create a work schedule for the project team to follow.

Answers
D.

Create a work schedule for the project team to follow.

Suggested answer: B

Explanation:

Identifying business needs and product descriptions is a crucial first step in project initiation, as it defines the project's purpose and scope. This step is in line with CompTIA Project+ practices for understanding and documenting project requirements.