Question 263 - PK0-005 discussion
A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay the project schedule. Which of the following should the project manager do first?
A.
Consult with the legal department.
B.
Update the issue log.
C.
Start a new RFP immediately.
D.
Perform a PERT analysis.