A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay the project schedule. Which of the following should the project manager do first?

A.

Consult with the legal department.

Answers
A.

Consult with the legal department.

B.

Update the issue log.

Answers
B.

Update the issue log.

C.

Start a new RFP immediately.

Answers
C.

Start a new RFP immediately.

D.

Perform a PERT analysis.

Answers
D.

Perform a PERT analysis.

Suggested answer: B

Explanation:

Updating the issue log is the first step in documenting the problem and determining its impact on the project. This aligns with CompTIA Project+ guidelines, which emphasize the importance of tracking issues as they arise.