During the progress of a project, the stakeholders require the delivery of multiple milestones with proper presentation of functionalities. Which of the following is the best methodology to use?

A.

Waterfall

Answers
A.

Waterfall

B.

SDLC

Answers
B.

SDLC

C.

XP

Answers
C.

XP

D.

Scrum

Answers
D.

Scrum

Suggested answer: D

Explanation:

Scrum is an agile methodology well-suited for projects that require frequent milestone deliveries and functionality demonstrations. It emphasizes iterative development, with regular presentations to stakeholders, which aligns with CompTIA Project+ principles for agile project management.