ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 265 - PK0-005 discussion

Report
Export

A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?

A.

Meet with the team and highlight the importance of change management.

Answers
A.

Meet with the team and highlight the importance of change management.

B.

Roll back the process and submit a change request.

Answers
B.

Roll back the process and submit a change request.

C.

Document the event as a lesson learned.

Answers
C.

Document the event as a lesson learned.

D.

Remove the team member who bypassed the CCB process.

Answers
D.

Remove the team member who bypassed the CCB process.

Suggested answer: A

Explanation:

Meeting with the team to emphasize the importance of following change management procedures is the best approach to prevent future unauthorized changes. CompTIA Project+ highlights the importance of adhering to formal change control processes to ensure project alignment and accountability.

asked 16/10/2024
Novka Mandic
35 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first