A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?
A.
Meet with the team and highlight the importance of change management.
B.
Roll back the process and submit a change request.
C.
Document the event as a lesson learned.
D.
Remove the team member who bypassed the CCB process.