Which of the following is the most important activity for the project manager during the closure of a project?

A.

Obtain project sign-off.

Answers
A.

Obtain project sign-off.

B.

Capture lessons learned.

Answers
B.

Capture lessons learned.

C.

Document historical information.

Answers
C.

Document historical information.

D.

Release resources.

Answers
D.

Release resources.

Suggested answer: A

Explanation:

Obtaining project sign-off is crucial in the closure phase, as it signifies formal acceptance of the project deliverables by the stakeholders. According to CompTIA Project+, project sign-off is a key milestone in officially closing the project.