A project manager provided details regarding the completion of the following tasks:

Equipment procurement took less time than estimated.

Equipment installation went according to schedule.

Which of the following should the project manager update?

A.

Change log

Answers
A.

Change log

B.

Project Gantt

Answers
B.

Project Gantt

C.

Issue log

Answers
C.

Issue log

D.

Requirements traceability matrix

Answers
D.

Requirements traceability matrix

Suggested answer: B

Explanation:

The Project Gantt chart is a scheduling tool used to track task progress and timelines. When tasks are completed ahead of schedule, updating the Gantt chart ensures accurate tracking. This aligns with CompTIA Project+ recommendations on project scheduling and monitoring.