Question 278 - PK0-005 discussion
A project manager provided details regarding the completion of the following tasks:
Equipment procurement took less time than estimated.
Equipment installation went according to schedule.
Which of the following should the project manager update?
A.
Change log
B.
Project Gantt
C.
Issue log
D.
Requirements traceability matrix