A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?

A.

Forcing

Answers
A.

Forcing

B.

Avoiding

Answers
B.

Avoiding

C.

Compromising

Answers
C.

Compromising

D.

Smoothing

Answers
D.

Smoothing

Suggested answer: A

Explanation:

Forcing is a conflict resolution technique where the project manager makes a decision unilaterally, without seeking consensus. According to CompTIA Project+, forcing may be used when time is critical, and decisions need to be made promptly.