Which of the following activities should a project manager perform during the closing phase? (Select three)

A.

Lessons learned

Answers
A.

Lessons learned

B.

Risk analysis

Answers
B.

Risk analysis

C.

Removing resources

Answers
C.

Removing resources

D.

Acquiring resources

Answers
D.

Acquiring resources

E.

Statement of work sign-off

Answers
E.

Statement of work sign-off

F.

Stakeholder analysis

Answers
F.

Stakeholder analysis

G.

Removing access

Answers
G.

Removing access

Suggested answer: A, C, G

Explanation:

During the closing phase, a project manager should conduct lessons learned sessions, release resources, and remove access. These actions align with CompTIA Project+ standards for project closure, focusing on finalizing project deliverables, releasing resources, and documenting insights.