Which of the following artifacts should project team members use if they want to identify who to communicate with and at what level?

A.

Concept of operations

Answers
A.

Concept of operations

B.

WBS

Answers
B.

WBS

C.

Integrated master schedule

Answers
C.

Integrated master schedule

D.

RACI

Answers
D.

RACI

Suggested answer: D

Explanation:

A RACI (Responsible, Accountable, Consulted, Informed) matrix clarifies roles and responsibilities, indicating who needs to be communicated with at various levels. CompTIA Project+ highlights RACI as a critical tool for effective project communication and accountability.