List of questions
Related questions
Question 286 - PK0-005 discussion
Which of the following artifacts should project team members use if they want to identify who to communicate with and at what level?
A.
Concept of operations
B.
WBS
C.
Integrated master schedule
D.
RACI
Your answer:
0 comments
Sorted by
Leave a comment first