During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?

A.

Status report

Answers
A.

Status report

B.

Issue log

Answers
B.

Issue log

C.

Risk report

Answers
C.

Risk report

D.

Risk register

Answers
D.

Risk register

Suggested answer: D

Explanation:

A risk register is used to document potential risks, including causes and impacts. This tool is essential for tracking and communicating project risks to stakeholders, as recommended by CompTIA Project+ for risk management.