Question 288 - PK0-005 discussion
Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?
A.
Risk
B.
Change
C.
Defect
D.
Issue