Question 289 - PK0-005 discussion
A project manager is meeting with business stakeholders to define the time frame for a go-live to occur without impacting business operations. Which of the following is the project manager working on?
A.
Validation check
B.
Downtime window schedule
C.
Customer notifications
D.
Risk analysis