ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 290 - PK0-005 discussion

Report
Export

Project A is running behind schedule. The team realizes that Project B is working on an API that was planned to be developed by Project A. The project manager from Project A decides to use the API from Project B. Which of the following risk management strategies describes this example?

A.

Exploit

Answers
A.

Exploit

B.

Share

Answers
B.

Share

C.

Transfer

Answers
C.

Transfer

D.

Accept

Answers
D.

Accept

Suggested answer: B

Explanation:

Sharing a resource like an API between projects to leverage each project's strengths and reduce duplicated efforts is a risk-sharing strategy. CompTIA Project+ outlines risk-sharing as a way to capitalize on opportunities or mitigate project constraints.

asked 16/10/2024
R. M.
33 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first