Question 31

Report
Export
Collapse

Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers to this question.

Production orders

Production orders

Planned orders (firmed)

Planned orders (firmed)

Planned orders (unfirmed)

Planned orders (unfirmed)

ATP quantities

ATP quantities

Suggested answer: A, B
asked 31/10/2024
Kenny McCue
32 questions

Question 32

Report
Export
Collapse

In your plant MRP is activated.

Which options do you have to exclude a material from the MRP run? Note: There are 2 correct answers to this question.

Use a specific MRP list.

Use a specific MRP list.

Use a specific material status.

Use a specific material status.

Use a specific material group.

Use a specific material group.

Use a specific MRP type.

Use a specific MRP type.

Suggested answer: B, D
asked 31/10/2024
Vladimir Litvinenko
29 questions

Question 33

Report
Export
Collapse

In documentation for MRP in Advanced Planning you read that new orders are created through infinite planning. What does this mean for the capacity requirements of a new order?

MRP assigns the capacity requirements automatically after the last scheduled operation for each work center.

MRP assigns the capacity requirements automatically after the last scheduled operation for each work center.

MRP creates the capacity requirements without considering existing load on the work centers.

MRP creates the capacity requirements without considering existing load on the work centers.

MRP creates the capacity requirements at the earliest possible time.

MRP creates the capacity requirements at the earliest possible time.

MRP assigns the capacity requirements automatically to work centers with the earliest available capacity.

MRP assigns the capacity requirements automatically to work centers with the earliest available capacity.

Suggested answer: A
asked 31/10/2024
Wasawatt Ch
39 questions

Question 34

Report
Export
Collapse

Which information is required when you create a product master in SAP S/4HANA Cloud Private Edition? Note: There are 2 correct answers to this question.

Base unit of measure

Base unit of measure

Industry sector

Industry sector

Selection screen for views

Selection screen for views

Product type

Product type

Suggested answer: A, B
asked 31/10/2024
William Hopson
31 questions

Question 35

Report
Export
Collapse

What could be the reason for different combinations of components in a multiple bill of material (BOM)? Note: There are 2 correct answers to this question.

Manufacturing date

Manufacturing date

BOM header status

BOM header status

BOM component status

BOM component status

Lot size

Lot size

Suggested answer: A, D
asked 31/10/2024
TienYai Ho
37 questions

Question 36

Report
Export
Collapse

What does the material type influence?

Note: There are 2 correct answers to this question.

Which document types class categories are allowed

Which document types class categories are allowed

Which plantspecific plantindependent statuses are allowed

Which plantspecific plantindependent statuses are allowed

Which material master screens appear in which sequence

Which material master screens appear in which sequence

Whether the material is produced inhouse procured externally or both

Whether the material is produced inhouse procured externally or both

Suggested answer: A, C
asked 31/10/2024
Gerrit Struik
54 questions

Question 37

Report
Export
Collapse

Which stard item categories can you select inside a bill of material (BOM)? Note: There are 2 correct answers to this question.

Variablesize item

Variablesize item

Work item

Work item

Preliminary item

Preliminary item

WBS item

WBS item

Suggested answer: A, C
asked 31/10/2024
Fthcx Fgghn
33 questions

Question 38

Report
Export
Collapse

Why would you use phantom assemblies?

Note: There are 3 correct answers to this question.

To simplify the structure of bills of material

To simplify the structure of bills of material

To reduce the number of changes required in bills of material

To reduce the number of changes required in bills of material

To reduce the number of material masters

To reduce the number of material masters

To make the assignment of components easier

To make the assignment of components easier

To increase the number of planning levels

To increase the number of planning levels

Suggested answer: A, B, D
asked 31/10/2024
Charles Manser
48 questions

Question 39

Report
Export
Collapse

What are the key features of using a low level code? Note: There are 2 correct answers to this question.

To determine the priority of alternative components inside ATP

To determine the priority of alternative components inside ATP

To determine how costs are rolled up by product costing

To determine how costs are rolled up by product costing

To determine the sequence in which materials are planned in MRP

To determine the sequence in which materials are planned in MRP

To determine the use of subitems inside material BOM (bill of material)

To determine the use of subitems inside material BOM (bill of material)

Suggested answer: B, C
asked 31/10/2024
Mustapha Amine Atmani
46 questions

Question 40

Report
Export
Collapse

You have maintained the parameters for simple discontinuation in the material master of a component.

Which business process will be affected if the available stock is zero the discontinuation date is in the past?

Back flushing

Back flushing

Kanban

Kanban

Material requirements planning

Material requirements planning

Production order release

Production order release

Suggested answer: C