Question 51

Report
Export
Collapse

Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA Cloud Private Edition. When can you use mode selection?

When several operations are maintained for one product

When several operations are maintained for one product

When alternative resources are used within one operation

When alternative resources are used within one operation

When several production versions are maintained for one product

When several production versions are maintained for one product

When multiple planned orders are scheduled in parallel on one resource

When multiple planned orders are scheduled in parallel on one resource

Suggested answer: B
asked 31/10/2024
Fatawu Musah
31 questions

Question 52

Report
Export
Collapse

You use planning strategy Finite Scheduling with Reverse want to allow scheduling in the past. How can you parameterize this in the strategy profile?

Specify a negative offset time.

Specify a negative offset time.

Specify a negative opening period.

Specify a negative opening period.

Specify a negative planning horizon.

Specify a negative planning horizon.

Specify a negative PP/DS horizon.

Specify a negative PP/DS horizon.

Suggested answer: A
asked 31/10/2024
Med Amine Aloui
26 questions

Question 53

Report
Export
Collapse

You are a consultant on an SAP S/4HANA Cloud brownfield project. In a meeting the customer decides to remodel an existing business process in accordance with clean core principles.

Which of the following SAP Signavio solutions can be used for the remodeling?

SAP Signavio Process Insights

SAP Signavio Process Insights

SAP Signavio Process Intelligence

SAP Signavio Process Intelligence

SAP Signavio Process Governance

SAP Signavio Process Governance

SAP Signavio Process Manager

SAP Signavio Process Manager

Suggested answer: C, D
asked 31/10/2024
MAXIM TEN
38 questions

Question 54

Report
Export
Collapse

You are a consultant on an SAP S/4HANA Cloud Greenfield project.

Which of the following aspects should you focus on to achieve maintain clean core data quality? Note: There are 2 correct answers to this question.

Efficiency

Efficiency

Accuracy

Accuracy

Timeliness

Timeliness

Stability

Stability

Suggested answer: A, D
asked 31/10/2024
João Faria
36 questions

Question 55

Report
Export
Collapse

What are some SAP recommended guiding principles to achieve clean core operations? Note: There are 3 correct answers to this question.

Establish an organizational structure technical foundation transformation methodology for clean core.

Establish an organizational structure technical foundation transformation methodology for clean core.

Integrate clean core practices in the endtoend value process chain.

Integrate clean core practices in the endtoend value process chain.

Establish release management.

Establish release management.

Establish regular housekeeping tasks procedures.

Establish regular housekeeping tasks procedures.

Define roles responsibilities as part of a process transformation office.

Define roles responsibilities as part of a process transformation office.

Suggested answer: A, C, E
asked 31/10/2024
Lebogang Aphane
44 questions

Question 56

Report
Export
Collapse

Which of the following are features of the clean core dashboard? Note: There are 2 correct answers to this question.

Customers can grant access to the dashboard to partners.

Customers can grant access to the dashboard to partners.

Customers can use the dashboard in the dev test production tenants.

Customers can use the dashboard in the dev test production tenants.

It can be accessed by using SAP For Me.

It can be accessed by using SAP For Me.

It can be used in all SAP S/4HANA Cloud editions.

It can be used in all SAP S/4HANA Cloud editions.

Suggested answer: A, C
asked 31/10/2024
Faria Sah
37 questions

Question 57

Report
Export
Collapse

What options does a planner have in the planning table for repetitive manufacturing? Note: There are 2 correct answers to this question.

Change the assignments of production quantities to production lines.

Change the assignments of production quantities to production lines.

Create new production quantities.

Create new production quantities.

Dispatch operations to work centers.

Dispatch operations to work centers.

Reschedule deallocate operations.

Reschedule deallocate operations.

Suggested answer: A, D
asked 31/10/2024
Jonathan Tang
42 questions

Question 58

Report
Export
Collapse

Where do you maintain the work center that represents the production line for repetitive manufacturing? Note: There are 2 correct answers to this question.

Production cost collector

Production cost collector

Production version

Production version

Repetitive manufacturing profile

Repetitive manufacturing profile

Routing

Routing

Suggested answer: B, D
asked 31/10/2024
Paul Bryant
30 questions

Question 59

Report
Export
Collapse

What are the prerequisites for a reporting point confirmation in repetitive manufacturing? Note: There are 2 correct answers to this question.

Become a Premium Member for full access
  Unlock Premium Member

Question 60

Report
Export
Collapse

Which options do you have to plan both quantities capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.