Question 164 - PMI-ACP discussion
During a review session an agile team presented done requirements to a group of stakeholders Stakeholder feedback indicated that the done requirements failed to meet the most pressing needs and provide value What should the team have done to prevent this?
A.
Reprioritized requirements prior to committing to iteration work
B.
Ensured that requirements remained stable during the iteration cycle
C.
Had stakeholders focus on items created after the product backlog was initially built
D.
Worked on features rather than a set of components