During project inception an agile practitioner engages the stakeholder to ensure alignment on the project's strategy and vision The stakeholder asks for detailed requirements design, and delivery plans What should the agile practitioner do?

A.
Provide all information requested by the stakeholder
Answers
A.
Provide all information requested by the stakeholder
B.
Set expectations regarding the appropriate level of details requested during this stage
Answers
B.
Set expectations regarding the appropriate level of details requested during this stage
C.
inform the stakeholder mat no detailed documents are provided using agile practices
Answers
C.
inform the stakeholder mat no detailed documents are provided using agile practices
D.
Ask the team to supply the information 10 the stakeholder
Answers
D.
Ask the team to supply the information 10 the stakeholder
Suggested answer: B