List of questions
Related questions
Question 163 - PMI-ACP discussion
A product owner asks a newly formed scrum team how many story points will be completed m a sprint What should the scrum master do?
A.
Engage the team to determine the sprint velocity based on previous agile projects
B.
Average the sprint velocity based on input from ream members
C.
Share the sprint velocity obtained from the sponsor with the team
D.
Run multiple sprints before determining the sprint velocity with the team.
Your answer:
0 comments
Sorted by
Leave a comment first