Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

A.
Benefits
Answers
A.
Benefits
B.
Quality
Answers
B.
Quality
C.
Risk
Answers
C.
Risk
D.
Scope
Answers
D.
Scope
Suggested answer: B

Explanation:

Quality is the aspect of project performance that must be managed to ensure the project's products are fit for purpose. PRINCE2 emphasizes that quality management is essential to ensure that the project outputs meet the necessary requirements and standards to achieve the desired outcomes.

Reference: PRINCE2 Foundation official documentation and study materials.

These responses are based on the latest materials and guidelines from the PRINCE2 Foundation, ensuring accurate and up-to-date answers as per your request.

asked 23/09/2024
Jessica Redmond
30 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first