Which is NOT included in the PRINCE2 definition of a project?

A.
A project is a temporary organization
Answers
A.
A project is a temporary organization
B.
A project's purpose is to deliver one or more business products
Answers
B.
A project's purpose is to deliver one or more business products
C.
A project is part of 'business as usual'
Answers
C.
A project is part of 'business as usual'
D.
A project is based on an agreed Business Case
Answers
D.
A project is based on an agreed Business Case
Suggested answer: C

Explanation:

According to PRINCE2, a project is not considered part of 'business as usual'. The defining attributes of a project include it being a temporary organization that is created for a specific purpose, which contrasts with 'business as usual' that involves ongoing, routine activities within an organization.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources