Which of the following is the Business Case used for during the Managing a Stage Boundary process?

A.
Enable the Project Board to decide whether or not to authorize the project
Answers
A.
Enable the Project Board to decide whether or not to authorize the project
B.
Justify the continuing viability of the project
Answers
B.
Justify the continuing viability of the project
C.
Enable the Project Board to decide whether or not to authorize project closure
Answers
C.
Enable the Project Board to decide whether or not to authorize project closure
D.
Justify the initiation of a project
Answers
D.
Justify the initiation of a project
Suggested answer: B

Explanation:

During the Managing a Stage Boundary process, the Business Case is used to justify the continuing viability of the project. This involves reviewing and, if necessary, updating the Business Case to reflect any changes or new insights that might impact the project's justification. This helps the Project Board make informed decisions about the future progression of the project.

Reference: PRINCE2 7 Foundation handbook and official documents.