Which activity takes place within the Managing a Stage Boundary process?

A.
Produce Highlight Reports
Answers
A.
Produce Highlight Reports
B.
Take corrective action within the limits of a stage's tolerance
Answers
B.
Take corrective action within the limits of a stage's tolerance
C.
Produce an Exception Plan
Answers
C.
Produce an Exception Plan
D.
Authorize a Stage Plan for the next stage
Answers
D.
Authorize a Stage Plan for the next stage
Suggested answer: C

Explanation:

Within the Managing a Stage Boundary process, one of the key activities is to produce an Exception Plan. This occurs when the current stage plan cannot be completed within the agreed tolerances. An Exception Plan is needed to replace the Stage Plan for the current stage and requires approval from the Project Board before it can be executed.

Reference: PRINCE2 7 Foundation resources and study materials.