Which is a purpose of a Project Brief?

A.
Enable the assembly of the project mandate
Answers
A.
Enable the assembly of the project mandate
B.
Describe the reporting requirements of the various layers of management involved with the project
Answers
B.
Describe the reporting requirements of the various layers of management involved with the project
C.
Describe how changes to products will be controlled
Answers
C.
Describe how changes to products will be controlled
D.
Provide a solid basis for the initiation of the project
Answers
D.
Provide a solid basis for the initiation of the project
Suggested answer: D

Explanation:

The purpose of a Project Brief in PRINCE2 is to provide a solid basis for the initiation of the project. The Project Brief includes the outline of the project's objectives, scope, constraints, and assumptions. It is developed during the 'Starting up a Project' process and is used to ensure that a clear, concise, and feasible plan is proposed before the project is formally initiated.

Reference: PRINCE2 7 Foundation resources and materials.