Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?

A.
Specify the desired result
Answers
A.
Specify the desired result
B.
Provide the resources and skills to deliver the desired result
Answers
B.
Provide the resources and skills to deliver the desired result
C.
Ensure the technical integrity of a project
Answers
C.
Ensure the technical integrity of a project
D.
Develop a project's products
Answers
D.
Develop a project's products
Suggested answer: A

Explanation:

In the PRINCE2 customer/supplier environment, it is typically the customer's responsibility to specify the desired result of the project. This responsibility involves defining what the project should achieve in terms of outcomes and benefits, aligning with the customer's business objectives.

Reference: PRINCE2 Foundation official study materials.