Which role is responsible for creating Checkpoint Reports?

A.
Senior Supplier
Answers
A.
Senior Supplier
B.
Team Manager
Answers
B.
Team Manager
C.
Change Authority
Answers
C.
Change Authority
D.
Project Support
Answers
D.
Project Support
Suggested answer: B

Explanation:

In PRINCE2, the Team Manager is responsible for creating Checkpoint Reports. These reports provide the Project Manager with a summary of the progress within a Work Package, detailing performance against plan, and highlighting any issues that might affect the work.