Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

A.
project cost tolerance
Answers
A.
project cost tolerance
B.
stage cost tolerance
Answers
B.
stage cost tolerance
C.
Work Package cost tolerance
Answers
C.
Work Package cost tolerance
D.
product cost tolerance
Answers
D.
product cost tolerance
Suggested answer: C

Explanation:

A Project Manager agrees on the Work Package cost tolerances with a Team Manager. This agreement defines the acceptable cost variance within which the Team Manager can operate without needing further approval.

Reference: PRINCE2 Foundation official study materials.