Question 105 - PRINCE2-7-Foundation discussion
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.
A.
project cost tolerance
B.
stage cost tolerance
C.
Work Package cost tolerance
D.
product cost tolerance
Your answer: