Question 118 - PRINCE2-7-Foundation discussion
Which of the following statements about quality assurance and Project Assurance is true?
A.
Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board
B.
Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager
C.
Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board
D.
Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization