Question 118 - PRINCE2-7-Foundation discussion

Report
Export

Which of the following statements about quality assurance and Project Assurance is true?

A.
Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board
Answers
A.
Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board
B.
Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager
Answers
B.
Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager
C.
Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board
Answers
C.
Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board
D.
Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization
Answers
D.
Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization
Suggested answer: D

Explanation:

Project Assurance in PRINCE2 is focused on the project's adherence to standards and procedures within the project environment, providing a project-level view of compliance. In contrast, Quality Assurance is an organizational level function that oversees compliance across all projects and operations, ensuring that the entire organization follows the prescribed standards.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.