Who carries out audits that are independent of the project?

A.
Quality assurance
Answers
A.
Quality assurance
B.
Project Assurance
Answers
B.
Project Assurance
C.
Project Support
Answers
C.
Project Support
D.
Project Manager
Answers
D.
Project Manager
Suggested answer: A

Explanation:

Quality assurance is responsible for carrying out independent audits within a project. These audits are designed to ensure that the project complies with external standards and internal policies at an organizational level, distinct from the project-focused activities.

Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.