Which is a purpose of the 'controlling a stage' process?

A.
To review the success of the project at the end of a management stage
Answers
A.
To review the success of the project at the end of a management stage
B.
To agree work package acceptance and delivery requirements
Answers
B.
To agree work package acceptance and delivery requirements
C.
To produce regular highlight reports for the project board
Answers
C.
To produce regular highlight reports for the project board
D.
To re-plan the current stage and the project when requested
Answers
D.
To re-plan the current stage and the project when requested
Suggested answer: C

Explanation:

The purpose of the 'controlling a stage' process in PRINCE2 is to ensure that the stage stays on course and reacts to unexpected events. Part of this process involves producing regular highlight reports for the project board, which summarizes the stage's progress, highlights any issues or risks, and keeps the board informed about ongoing activities.

Reference: PRINCE2 Foundation Manual