Which process provides information for the project board to review an updated project plan?

A.
Initiating a project
Answers
A.
Initiating a project
B.
Controlling a stage
Answers
B.
Controlling a stage
C.
Directing a project
Answers
C.
Directing a project
D.
Managing a stage boundary
Answers
D.
Managing a stage boundary
Suggested answer: D

Explanation:

The process that provides information for the project board to review an updated project plan is 'Managing a Stage Boundary'. This process involves preparing the information needed for the project board to review the current stage's performance, reassess the project viability, and make decisions regarding the next stage, including updates to the project plan if necessary.

Reference: PRINCE2 Foundation Manual