Which is a purpose of the 'initiating a project' process?

A.
To ensure the project has a sound basis before asking the project board to authorize the project
Answers
A.
To ensure the project has a sound basis before asking the project board to authorize the project
B.
To authorize the stage plan for the next management stage of the project
Answers
B.
To authorize the stage plan for the next management stage of the project
C.
To establish a contract between the project management team and the commissioning organization
Answers
C.
To establish a contract between the project management team and the commissioning organization
D.
To ensure that prerequisites are in place before starting the project
Answers
D.
To ensure that prerequisites are in place before starting the project
Suggested answer: A

Explanation:

The purpose of the 'Initiating a Project' process in PRINCE2 is to ensure that the project has a sound basis before the project board is asked to make any major commitment to the project. This process is crucial for establishing a stable foundation for the project, detailing the necessary aspects such as scope, timescales, costs, risks, and benefits before full-scale implementation commences.

Reference: PRINCE2 Foundation Manual