Question 336 - PRINCE2-7-Foundation discussion
How should the 'managing a stage boundary' process be used towards the end of a project's final delivery stage?
A.
To plan the activities of the closing a project' process
B.
To implement any exception plan requests from the project board
C.
To create a benefits management approach for corporate, programme management or the customer
D.
To review an issue received from a team manager