Question 337 - PRINCE2-7-Foundation discussion
How often should the 'controlling a stage' process be used during a project?
A.
Once, for the whole project
B.
For each delivery stage in the project
C.
Whenever the project board meets
D.
Twice, for initiation and for the rest of the project
Your answer: