How often should the 'controlling a stage' process be used during a project?

A.
Once, for the whole project
Answers
A.
Once, for the whole project
B.
For each delivery stage in the project
Answers
B.
For each delivery stage in the project
C.
Whenever the project board meets
Answers
C.
Whenever the project board meets
D.
Twice, for initiation and for the rest of the project
Answers
D.
Twice, for initiation and for the rest of the project
Suggested answer: B

Explanation:

The 'Controlling a Stage' process should be used during each delivery stage of a project. This process is essential for the day-to-day management of the project stage by the project manager. It includes monitoring, reporting, and responding to issues within the stage to ensure the project remains within agreed tolerances.

Reference: = PRINCE2 7 Foundation handbook and online resources