Question 338 - PRINCE2-7-Foundation discussion

Report
Export

Which process is used by the project board to respond to on exception report?

A.
Controlling a stage
Answers
A.
Controlling a stage
B.
Managing a stage boundary
Answers
B.
Managing a stage boundary
C.
Managing product delivery
Answers
C.
Managing product delivery
D.
Directing a project
Answers
D.
Directing a project
Suggested answer: D

Explanation:

The 'Directing a Project' process is used by the project board to respond to an exception report. This process involves the project board making decisions on how to proceed when project tolerances are forecasted to be exceeded, which are typically communicated through an exception report.

Reference: = PRINCE2 7 Foundation handbook and online resources