When is the 'managing a stage boundary' process used?

A.
Immediately alter the project board has authorized the previous stage
Answers
A.
Immediately alter the project board has authorized the previous stage
B.
Immediately after the project board has authorized the next stage
Answers
B.
Immediately after the project board has authorized the next stage
C.
Near the end of each stage
Answers
C.
Near the end of each stage
D.
Near the end of delivery stages
Answers
D.
Near the end of delivery stages
Suggested answer: C

Explanation:

The 'Managing a Stage Boundary' process is used near the end of each stage of a project. This process includes the review of the current stage, preparation for the project board to authorize the next stage, updating a project plan, and, if necessary, updating the business case and project initiation documentation.

Reference: = PRINCE2 7 Foundation handbook and online resources