Which statement describes the context of the 'initiating a project' process?

A.
The project is viewed from the perspective of the project board in this process
Answers
A.
The project is viewed from the perspective of the project board in this process
B.
This process should result in key stakeholders being committed to the project
Answers
B.
This process should result in key stakeholders being committed to the project
C.
This process is triggered by the assembly of the project brief
Answers
C.
This process is triggered by the assembly of the project brief
D.
The 'controlling a stage' process will start immediately after this process
Answers
D.
The 'controlling a stage' process will start immediately after this process
Suggested answer: A

Explanation:

During the 'Initiating a Project' process in PRINCE2, the project is considered from the perspective of the project board. This process ensures that the project board has all the necessary information to commit to the project, understanding its scope, timescales, costs, risks, and overall approach before granting formal approval to proceed.

Reference: PRINCE2 Foundation Manual